Progress timeline

June 2016

Central core ready for steelwork

Read more

May 2016

Block ‘B’ nearing roof level

Read more

April 2016

Block ‘B’ progressing again

Read more

March 2016

Roof structure to block ‘A’ nearing completion

Read more

February 2016

Works underway again

Read more

January 2016

Site closed up after contractor went into liquidation

Read more

November 2015

Last section of formwork to complete the basement walls

Read more

November 2015

Video Report

October 2015

Basement backfilled and ground floor walls built above

Read more

September 2015

North wing reaches roof level, roof structure starts next week

Read more

September 2015

Video Report

August 2015

North wing reaches second floor level

Read more

July 2015

Basement finally nearing completion

Read more

July 2015

Video Report

June 2015

Video Report

June 2015

Ground floor blockwork progressing well

Read more

May 2015

Video Report

May 2015

Basement excavation nearing completion

Read more